Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Aug 10, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Painting HARDIE SIDING - All Elevations
- Complete Refrigerant Piping / Pressure Testing out to Mechanical Yard
- Start Setting Storefront Window Glass @ Lobby
- Complete Plumbing Pipe Insulation for Sheetrock Cover-up
- Start Tape & Float @ Council Chamber & Lobby
- Dropped Fire Sprinkler Heads into Sheetrock Ceiling Framing

Complete Painting HARDIE SIDING
NEXT WEEK'S ACTIVITIES
- Complete Downspout Roof Drain Grate Installation
- Continue Tape / Float/ Sanding / Prime Coat @ Council Chamber & Lobby
- Complete 85% Window Glass Installation @ Storefront Frames
- Continue Metal Vented Soffit Installation
- Receive O/H Fire Sprinkler Cover-up Inspection @ Sheetrock Ceiling Assemblies

- Start Exterior Metal Wall Panels
Start Metal Vented Soffit Panels

Start Installation of Window Glass @ Lobby
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.