Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Aug 10, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Painting HARDIE SIDING - All Elevations
    Complete Refrigerant Piping / Pressure Testing out to Mechanical Yard
    Start Setting Storefront Window Glass @ Lobby
    Complete Plumbing Pipe Insulation for Sheetrock Cover-up
    Start Tape & Float @ Council Chamber & Lobby
    Dropped Fire Sprinkler Heads into Sheetrock Ceiling Framing
Excavation 1.jpg

Complete Painting HARDIE SIDING

NEXT WEEK'S ACTIVITIES

    Complete Downspout Roof Drain Grate Installation
    Continue Tape / Float/ Sanding / Prime Coat @ Council Chamber & Lobby
    Complete 85% Window Glass Installation @ Storefront Frames
    Continue Metal Vented Soffit Installation
    Receive O/H Fire Sprinkler Cover-up Inspection @ Sheetrock Ceiling Assemblies
Excavation 1.jpg
    Start Exterior Metal Wall Panels

Start Metal Vented Soffit Panels

Excavation 1.jpg

Start Installation of Window Glass @ Lobby

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.