Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Nov 9, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Fire Alarm Pre-Test Inspection
    Start-up of 85% of Mechanical A/C Equipment
    Start Installing Stone Countertops to 70%
    Install Spiral Duct @ Council Chamber Plan East
    Energize Lights @ Plan West Wing Core Storage Rooms & Restrooms
    Start Cable Tray Installation @ IT Room
Excavation 1.jpg

Millwork with Stone Countertop Installation - Typical

NEXT WEEK'S ACTIVITIES

    Complete Millwork Installation
    Start Epoxy Floor Prep @ Plan East Restrooms
    Start Final Paint @ Plan West Wing Storage Rooms & Offices
    Energize 70% Plan West Wing Light Fixtures
    Continue Stone Countertop & Backsplash Installation
Excavation 1.jpg
    Install Pendant Drops for Council Chamber Lights

Start Cable Tray / Equipment Rack @ IT Room

Excavation 1.jpg

Install Spiral Duct @ Council Chamber Plan East

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.