top of page


Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Nov 9, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Fire Alarm Pre-Test Inspection
- Start-up of 85% of Mechanical A/C Equipment
- Start Installing Stone Countertops to 70%
- Install Spiral Duct @ Council Chamber Plan East
- Energize Lights @ Plan West Wing Core Storage Rooms & Restrooms
- Start Cable Tray Installation @ IT Room

Millwork with Stone Countertop Installation - Typical
NEXT WEEK'S ACTIVITIES
- Complete Millwork Installation
- Start Epoxy Floor Prep @ Plan East Restrooms
- Start Final Paint @ Plan West Wing Storage Rooms & Offices
- Energize 70% Plan West Wing Light Fixtures
- Continue Stone Countertop & Backsplash Installation

- Install Pendant Drops for Council Chamber Lights
Start Cable Tray / Equipment Rack @ IT Room

Install Spiral Duct @ Council Chamber Plan East
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page