Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Nov 2, 2025

THIS WEEK'S ACCOMPLISHMENT

    Begin Start-up of Mechanical Units
    Complete Ceiling Grid @ Lobby
    Continue Ceiling Border Tile Installation
    Start Millwork Installation
    Install Sliding Glass Doors @ Breakroom
    Install Ground Sleeves for Flagpoles
Excavation 1.jpg

Install 85% Mechanical Yard Fence & Gate

NEXT WEEK'S ACTIVITIES

    Complete Fire Alarm System & PRE-TEST
    Continue Start-up of All Mechanical A/C Equipment
    Start Setting Stone Countertops
    Complete 90% of Ceiling Tile Borders
    Energize Lights to Restrooms and Plan West Wing Storage Rooms
Excavation 1.jpg
    Pour Monument Sign Concrete Foundation

Start Millwork Installation @ Room #114

Excavation 1.jpg

Install Sliding Glass Doors @ Breakroom

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.