THIS WEEK'S ACCOMPLISHMENT
- Begin Start-up of Mechanical Units
- Complete Ceiling Grid @ Lobby
- Continue Ceiling Border Tile Installation
- Start Millwork Installation
- Install Sliding Glass Doors @ Breakroom
- Install Ground Sleeves for Flagpoles

Install 85% Mechanical Yard Fence & Gate
NEXT WEEK'S ACTIVITIES
- Complete Fire Alarm System & PRE-TEST
- Continue Start-up of All Mechanical A/C Equipment
- Start Setting Stone Countertops
- Complete 90% of Ceiling Tile Borders
- Energize Lights to Restrooms and Plan West Wing Storage Rooms

- Pour Monument Sign Concrete Foundation
Start Millwork Installation @ Room #114

Install Sliding Glass Doors @ Breakroom