top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Jul 6, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Metal Wall Panels @ Top of Chimney
    Pressure Test Fire Sprinkler Main & Branch Lines
    Continue Top-out of Sheetrock @ Council Chamber
    Pressure Test All Refrigerant Lines up to South Wing Mezzanine
    Install Fire Rated Backer Board on All I.T. Walls for Data Cabling
    Complete 80% of Duct @ South Wing Mezzanine
Excavation 1.jpg

Complete Metal Wall Panels @ North Wing Chimney

NEXT WEEK'S ACTIVITIES

    Complete Standing Seam Panels @ North Upper Wing
    Finish Top-out of Sheetrock @ Council Chamber
    Complete South Wing Plumbing Rough with City Inspection
    Install Sheetrock Ceiling Framing to 60%
    Pump Down Pond #2 due to RAIN
Excavation 1.jpg
    Complete Waterproofing for South Wing Upper Gable Window Installation

Install Fire Rated Backer Board for I.T. Data Cabling

Excavation 1.jpg

Complete South Wing Mezzanine Duct Work to 80%

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page