Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Oct 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Brick Pavers @ Main Entry
- Complete Vented Metal Soffits @ Roof
- Start Extending Refrigerant Piping to Condensers
- Final Grading @ Water Quality Pond #1 & #2
- Install Exterior Light Fixtures
- Start Ceramic Tile Installation

Extend Refrigerant Piping to Condensers @ Mechanical Yard
NEXT WEEK'S ACTIVITIES
- Start Irrigation & Landscape Installation
- Complete Water Quality Pond #1 & #2 Construction
- Continue Ceramic Tile Installation @ Restrooms
- Pull Secondary Electric Wire to Building Disconnect & Energize
- Complete Ceiling Grid Installation @ Lobby

- Start Fire Alarm System Installation
Start Ceramic Tile Installation @ Restrooms

Complete Brick Pavers @ Main Entry
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.