THIS WEEK'S ACCOMPLISHMENT

    Complete Brick Pavers @ Main Entry
    Complete Vented Metal Soffits @ Roof
    Start Extending Refrigerant Piping to Condensers
    Final Grading @ Water Quality Pond #1 & #2
    Install Exterior Light Fixtures
    Start Ceramic Tile Installation
Excavation 1.jpg

Extend Refrigerant Piping to Condensers @ Mechanical Yard

NEXT WEEK'S ACTIVITIES

    Start Irrigation & Landscape Installation
    Complete Water Quality Pond #1 & #2 Construction
    Continue Ceramic Tile Installation @ Restrooms
    Pull Secondary Electric Wire to Building Disconnect & Energize
    Complete Ceiling Grid Installation @ Lobby
Excavation 1.jpg
    Start Fire Alarm System Installation

Start Ceramic Tile Installation @ Restrooms

Excavation 1.jpg

Complete Brick Pavers @ Main Entry