Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Sep 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    Start Exterior Metal Wall Panels @ Plan East Restrooms
    Complete Lightning Protection System
    Complete Plan West Low Roof Vented Metal Soffit
    Complete 1st Finish Coat Paint @ Lobby & Council Chamber
    Continue Storefront Caulking & Trim
    Start Installation of Office Light Fixture
Excavation 1.jpg

Paint Dumpster Enclosure

NEXT WEEK'S ACTIVITIES

    Complete Final (3) Small Room Ceiling Grid
    Continue Light Fixture Installation at West Wing Rooms
    Install Sidewalk & PEC Transformer Service Landing
    Complete Interior Storefront Door Frame Installation
    Complete Metal Wall Panels @ Patio
Excavation 1.jpg
    Complete Dropping Sprinkler Heads @ All Rooms

Complete Vented Metal Soffit @ Plan West Wing Low Roof

Excavation 1.jpg

Start Metal Wall Panels @ Plan East Restrooms

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page