Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Sep 7, 2025
THIS WEEK'S ACCOMPLISHMENT
- Start Exterior Metal Wall Panels @ Plan East Restrooms
- Complete Lightning Protection System
- Complete Plan West Low Roof Vented Metal Soffit
- Complete 1st Finish Coat Paint @ Lobby & Council Chamber
- Continue Storefront Caulking & Trim
- Start Installation of Office Light Fixture

Paint Dumpster Enclosure
NEXT WEEK'S ACTIVITIES
- Complete Final (3) Small Room Ceiling Grid
- Continue Light Fixture Installation at West Wing Rooms
- Install Sidewalk & PEC Transformer Service Landing
- Complete Interior Storefront Door Frame Installation
- Complete Metal Wall Panels @ Patio

- Complete Dropping Sprinkler Heads @ All Rooms
Complete Vented Metal Soffit @ Plan West Wing Low Roof

Start Metal Wall Panels @ Plan East Restrooms
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.