THIS WEEK'S ACCOMPLISHMENT

    Prepare Site for City's 20th Anniversary Celebration
    Hydro-Seed Water Quality Ponds #1 & #2
    Installed Fire Alarm Devices
    Install SL-1 Exterior Light Poles at Plan South Elevation
    Set Limestone Blocks @ Entry
    Start Installation of Ceiling Tile Borders
Excavation 1.jpg

Set Limestone Blocks @ Entry

NEXT WEEK'S ACTIVITIES

    Complete Ceiling Grid @ Lobby
    Install 50% of Ceiling Tile @ Lobby & Council Chamber
    Complete Storefront Assemblies to 98%
    Begin Start-up of all Mechanical Equipment
    Start Millwork Installation
Excavation 1.jpg
    Start Plumbing Fixture Installation

Install SL-1 Light Poles

Excavation 1.jpg

Hydro-Seed Water Quality Ponds #1 & #2