THIS WEEK'S ACCOMPLISHMENT
- Prepare Site for City's 20th Anniversary Celebration
- Hydro-Seed Water Quality Ponds #1 & #2
- Installed Fire Alarm Devices
- Install SL-1 Exterior Light Poles at Plan South Elevation
- Set Limestone Blocks @ Entry
- Start Installation of Ceiling Tile Borders

Set Limestone Blocks @ Entry
NEXT WEEK'S ACTIVITIES
- Complete Ceiling Grid @ Lobby
- Install 50% of Ceiling Tile @ Lobby & Council Chamber
- Complete Storefront Assemblies to 98%
- Begin Start-up of all Mechanical Equipment
- Start Millwork Installation

- Start Plumbing Fixture Installation
Install SL-1 Light Poles

Hydro-Seed Water Quality Ponds #1 & #2
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.