THIS WEEK'S ACCOMPLISHMENT

    Complete Concrete Flatwork @ Patio
    Complete Remaining Plan South Sidewalks
    Complete Final Grading Prior to Irrigation / Landscape
    Complete All Remaining Sheetrock Ceilings
    Continue Quality Pond Construction
    Receive & Set Outside A/C Condenser Units
Excavation 1.jpg

Final Grading @ Water Quality Pond #2

NEXT WEEK'S ACTIVITIES

    Continue Quality Pond Construction
    Extend Refrigerant Piping to Outside Condenser Units
    Complete All Misc. Concrete Placement: Bollards, Pole Base, Raised Flooring
    Start U/G Irrigation Piping
    Start Ceramic Tile @ Plan West Restrooms
Excavation 1.jpg
    Pull Fire Alarm Wiring

Exterior A/C Condensers @ Mechanical Yard

Excavation 1.jpg

Complete Concrete Sidewalks @ Plan South