Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Sep 28, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Concrete Flatwork @ Patio
- Complete Remaining Plan South Sidewalks
- Complete Final Grading Prior to Irrigation / Landscape
- Complete All Remaining Sheetrock Ceilings
- Continue Quality Pond Construction
- Receive & Set Outside A/C Condenser Units

Final Grading @ Water Quality Pond #2
NEXT WEEK'S ACTIVITIES
- Continue Quality Pond Construction
- Extend Refrigerant Piping to Outside Condenser Units
- Complete All Misc. Concrete Placement: Bollards, Pole Base, Raised Flooring
- Start U/G Irrigation Piping
- Start Ceramic Tile @ Plan West Restrooms

- Pull Fire Alarm Wiring
Exterior A/C Condensers @ Mechanical Yard

Complete Concrete Sidewalks @ Plan South
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.