top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Jul 20, 2025

THIS WEEK'S ACCOMPLISHMENT

    Flush Out 6" Fire Line & Connect to Building Fire Riser Assembly
    Complete Sheetrock Top-out @ Council Chamber & Lobby
    Complete Hardie Board Siding @ Plan East Wing - N,S & E Walls
    Install Standing Seam Roof Panels @ Plan East - North Lower Roof
    Start Tape & Float @ Plan East Wing Offices
    Start Storefront Window Frame Assemblies @ Breakroom #123 & Medium Conference #112
Excavation 1.jpg

6" Fire Line Flushing

NEXT WEEK'S ACTIVITIES

    Install Storm Line Near Flagpole & Under Paver Walkway
    Continue Installation of Storefront Window Frames Assemblies
    Complete Standing Seam Metal Panels @ Lower Plan East Wing Roof
    Complete Hardie Siding @ Lower Plan East Wing Roof
    Continue Tape - Float - Sanding @ Plan East Wing Offices
Excavation 1.jpg
    Install Ceiling Framing Grid Above Council Chamber Dais

Storefront Window Framing Installation @ Breakroom #123

Excavation 1.jpg

Sheetrock Top-out @ Council Chamber

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page