Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Jul 20, 2025
THIS WEEK'S ACCOMPLISHMENT
- Flush Out 6" Fire Line & Connect to Building Fire Riser Assembly
- Complete Sheetrock Top-out @ Council Chamber & Lobby
- Complete Hardie Board Siding @ Plan East Wing - N,S & E Walls
- Install Standing Seam Roof Panels @ Plan East - North Lower Roof
- Start Tape & Float @ Plan East Wing Offices
- Start Storefront Window Frame Assemblies @ Breakroom #123 & Medium Conference #112

6" Fire Line Flushing
NEXT WEEK'S ACTIVITIES
- Install Storm Line Near Flagpole & Under Paver Walkway
- Continue Installation of Storefront Window Frames Assemblies
- Complete Standing Seam Metal Panels @ Lower Plan East Wing Roof
- Complete Hardie Siding @ Lower Plan East Wing Roof
- Continue Tape - Float - Sanding @ Plan East Wing Offices

- Install Ceiling Framing Grid Above Council Chamber Dais
Storefront Window Framing Installation @ Breakroom #123

Sheetrock Top-out @ Council Chamber
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.