Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Sep 14, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continue Flatwork Grading @ Patio Prior to Concrete Placement
- Continue Breakmetal & Sealant @ Lobby Storefront Window Assembly
- Complete Interior Office Storefront Door Frame Assemblies
- Complete Exterior Metal Wall Panels @ Plan South Patio
- Complete Fire Sprinkler Head Installation in Ceiling Grid
- Continue High Ceiling Grid Installation @ Council Chamber

High Ceiling Grid @ Council Chamber
NEXT WEEK'S ACTIVITIES
- Pour Flatwork @ Lobby Patio Entry & Christmas Tree
- Schedule Fire Sprinkler Hydro Test / Inspection
- Continue High Ceiling Grid Installation @ Lobby
- Continue Sheetrock Ceiling Installation @ Dais & Plan East Restrooms
- Continue Installation of Light Fixture Can Lights

- Start Water Quality Pond #1 Installation
Final Grading For Concrete Flatwork @ Patio

90% Completion of Metal Wall Panels @ Patio