Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Sep 14, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continue Flatwork Grading @ Patio Prior to Concrete Placement
    Continue Breakmetal & Sealant @ Lobby Storefront Window Assembly
    Complete Interior Office Storefront Door Frame Assemblies
    Complete Exterior Metal Wall Panels @ Plan South Patio
    Complete Fire Sprinkler Head Installation in Ceiling Grid
    Continue High Ceiling Grid Installation @ Council Chamber
Excavation 1.jpg

High Ceiling Grid @ Council Chamber

NEXT WEEK'S ACTIVITIES

    Pour Flatwork @ Lobby Patio Entry & Christmas Tree
    Schedule Fire Sprinkler Hydro Test / Inspection
    Continue High Ceiling Grid Installation @ Lobby
    Continue Sheetrock Ceiling Installation @ Dais & Plan East Restrooms
    Continue Installation of Light Fixture Can Lights
Excavation 1.jpg
    Start Water Quality Pond #1 Installation

Final Grading For Concrete Flatwork @ Patio

Excavation 1.jpg

90% Completion of Metal Wall Panels @ Patio

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.