Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Aug 3, 2025
THIS WEEK'S ACCOMPLISHMENT
- CoHB Plumbing Contractor Set Waste Tank for Grinder Pumps
- Complete HARDIE SIDING @ Plan West Ground Elevation
- Complete Main Metal Standing Seam Roof Panels @ Plan East Lower Roof
- Continue Storefront Window Frame Installation @ Main Lobby Entry
- Complete Connecting Refrigerant Line Sets to Mixing Boxes @ Plan West Mezzanine
- Complete Pressure Test & CoHB Inspection of Water Piping System

Waste Tank Installation by CoHB Plumbing Contractor
NEXT WEEK'S ACTIVITIES
- Complete Painting of Exterior HARDIE SIDING
- Start Glass Installation @ Storefront Window Assemblies
- Complete Connection / Pressure Testing of Refrigerant Lines Sets @ Mechanical Yard
- Complete Plumbing Pipe Insulation
- Complete Dropping Fire Sprinkler Heads in Sheetrock Ceilings

- Continue Tape, Float, Sanding, Prime & 1st Finish Paint @ Plan West Wing.
Refrigerant Line Set Connection to Mixing Box

Storefront Window Frame Installation @ Lobby
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.