Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Aug 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    CoHB Plumbing Contractor Set Waste Tank for Grinder Pumps
    Complete HARDIE SIDING @ Plan West Ground Elevation
    Complete Main Metal Standing Seam Roof Panels @ Plan East Lower Roof
    Continue Storefront Window Frame Installation @ Main Lobby Entry
    Complete Connecting Refrigerant Line Sets to Mixing Boxes @ Plan West Mezzanine
    Complete Pressure Test & CoHB Inspection of Water Piping System
Excavation 1.jpg

Waste Tank Installation by CoHB Plumbing Contractor

NEXT WEEK'S ACTIVITIES

    Complete Painting of Exterior HARDIE SIDING
    Start Glass Installation @ Storefront Window Assemblies
    Complete Connection / Pressure Testing of Refrigerant Lines Sets @ Mechanical Yard
    Complete Plumbing Pipe Insulation
    Complete Dropping Fire Sprinkler Heads in Sheetrock Ceilings
Excavation 1.jpg
    Continue Tape, Float, Sanding, Prime & 1st Finish Paint @ Plan West Wing.

Refrigerant Line Set Connection to Mixing Box

Excavation 1.jpg

Storefront Window Frame Installation @ Lobby

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.