Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Aug 17, 2025
THIS WEEK'S ACCOMPLISHMENT
- Receive O/H Inspection for Fire Sprinkler @ Sheetrock Ceilings
- Installation of Panel Cans @ Electric Room #138
- Continue Sand - Prime - 1st Finish Coat Paint @ West Wing Corridors
- Complete 85% Glass Installation @ Storefront Windows
- Complete Vented Metal Soffit Panels @ Upper West Wing Roof
- Complete Downspout Ground Grates

Install Spring Vibration Isolators @ Office A/C Units - Typical
NEXT WEEK'S ACTIVITIES
- Complete 95% Window Glass Installation
- Continue Metal Soffit Installation @ Plan East Wing Roofing
- Install Forms & Rebar for Raised Concrete Floors @ #108 & DAIS
- Start Final Exterior Flatwork - Including Christmas Tree Area
- Start Sanding, Prime & 1st Finish Coat @ Council Chamber & Lobby

- Start Acoustical Ceiling Grid @ Plan West Offices
Install Panel Cans @ Electric Room #138

Complete Vented Metal Soffit Panels @ Plan West Upper Roof
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.