top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Aug 17, 2025

THIS WEEK'S ACCOMPLISHMENT

    Receive O/H Inspection for Fire Sprinkler @ Sheetrock Ceilings
    Installation of Panel Cans @ Electric Room #138
    Continue Sand - Prime - 1st Finish Coat Paint @ West Wing Corridors
    Complete 85% Glass Installation @ Storefront Windows
    Complete Vented Metal Soffit Panels @ Upper West Wing Roof
    Complete Downspout Ground Grates
Excavation 1.jpg

Install Spring Vibration Isolators @ Office A/C Units - Typical

NEXT WEEK'S ACTIVITIES

    Complete 95% Window Glass Installation
    Continue Metal Soffit Installation @ Plan East Wing Roofing
    Install Forms & Rebar for Raised Concrete Floors @ #108 & DAIS
    Start Final Exterior Flatwork - Including Christmas Tree Area
    Start Sanding, Prime & 1st Finish Coat @ Council Chamber & Lobby
Excavation 1.jpg
    Start Acoustical Ceiling Grid @ Plan West Offices

Install Panel Cans @ Electric Room #138

Excavation 1.jpg

Complete Vented Metal Soffit Panels @ Plan West Upper Roof

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page