Weekly Project Update

Horseshoe Bay City Hall

Placeholder

Nathan Barry

Jun 29, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete Fire Sprinkler Main & Branch Piping Installation
    Complete Thin Stone Masonry @ North Wing Chimney
    Complete 98% of Interior Masonry Thin Stone @ Council Chamber & Lobby
    Complete Refrigerant Line Sets from Room #103A Bldg. Entry to South Wing Mezzanine
    Complete 70% Two Siding Sheetrock @ South Wing Rooms
    Complete 65% Equipment & Duct Installation @ South Wing Mezzanine
Excavation 1.jpg

65% Equipment & Duct @ South Wing Mezzanine

NEXT WEEK'S ACTIVITIES

    Pressure Test Refrigerant Line Sets from Mech. Yard to South Wing Mezzanine
    Start Ceiling Framing over Dais in Council Chamber
    Complete 85% Two Siding Sheetrock All South Wing Rooms
    Complete Metal Panels & Standing Seam Roofing @ Chimney
    Complete Duct @ South Wing Mezzanine to 80%
Excavation 1.jpg
    Air Pressure Testing of Fire Sprinkler Main & Branch Piping

Refrigerant Piping under Mech. Platform above Dais

Excavation 1.jpg

Masonry Thin Store Completed @ 'Chimney'

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.