Weekly Project Update
Horseshoe Bay City Hall

Nathan Barry
Jun 29, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete Fire Sprinkler Main & Branch Piping Installation
- Complete Thin Stone Masonry @ North Wing Chimney
- Complete 98% of Interior Masonry Thin Stone @ Council Chamber & Lobby
- Complete Refrigerant Line Sets from Room #103A Bldg. Entry to South Wing Mezzanine
- Complete 70% Two Siding Sheetrock @ South Wing Rooms
- Complete 65% Equipment & Duct Installation @ South Wing Mezzanine

65% Equipment & Duct @ South Wing Mezzanine
NEXT WEEK'S ACTIVITIES
- Pressure Test Refrigerant Line Sets from Mech. Yard to South Wing Mezzanine
- Start Ceiling Framing over Dais in Council Chamber
- Complete 85% Two Siding Sheetrock All South Wing Rooms
- Complete Metal Panels & Standing Seam Roofing @ Chimney
- Complete Duct @ South Wing Mezzanine to 80%

- Air Pressure Testing of Fire Sprinkler Main & Branch Piping
Refrigerant Piping under Mech. Platform above Dais

Masonry Thin Store Completed @ 'Chimney'
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.