THIS WEEK'S ACCOMPLISHMENT
- Place Concrete @ Lobby Entry & Christmas Tree
- Pre-Test Fire Sprinkler System with Water
- Complete High Ceiling Grid @ Council Chamber
- Continue Sheetrock Plan West Restroom Ceilings
- Complete Light Fixture Installation in Office Ceiling Grid
- Complete Metal Soffit Panels @ Patio

Complete Metal Soffit Panels @ Patio & Lobby Entry
NEXT WEEK'S ACTIVITIES
- Complete Placing Concrete Flatwork @ Patio
- Complete Plan South Sidewalks
- Complete Final Site Grading Prior to Irrigation / Landscaping
- Complete Any / All Remaining Sheetrock Ceilings
- Continue Water Pond Construction

- Receive and Set Mechanical Yard Condensers