top of page


Weekly Project Update
Horseshoe Bay Fire Station No. 2, 07/03/2025

Michael Olmos
Jul 3, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished installation of stone veneer and cap stone at mechanical pad
- Finished installation of overhead fire sprinkler system rough in
- Continued installation of exterior stone veneer around the building
- Continued installation of overhead MEP rough in
- Started installation of overhead roofing insulation
- Completed roughly 90% of roofing panel system installation

Overhead HVAC duct installed above Day Room
NEXT WEEK'S ACTIVITIES
- Finish installation of exterior stone veneer around the building
- Finish installation of overhead roofing insulation
- Continue installation of overhead MEP rough in
- Start installation of exterior hardi siding
-

-
Stone veneer progressing around plan-East side of building outside of living quarters

Roughly 90% of the roofing panel system is installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page