Weekly Project Update

Horseshoe Bay Fire Station No. 2, 07/03/2025

Placeholder

Michael Olmos

Jul 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished installation of stone veneer and cap stone at mechanical pad
    Finished installation of overhead fire sprinkler system rough in
    Continued installation of exterior stone veneer around the building
    Continued installation of overhead MEP rough in
    Started installation of overhead roofing insulation
    Completed roughly 90% of roofing panel system installation
Excavation 1.jpg

Overhead HVAC duct installed above Day Room

NEXT WEEK'S ACTIVITIES

    Finish installation of exterior stone veneer around the building
    Finish installation of overhead roofing insulation
    Continue installation of overhead MEP rough in
    Start installation of exterior hardi siding
Excavation 1.jpg

Stone veneer progressing around plan-East side of building outside of living quarters

Excavation 1.jpg

Roughly 90% of the roofing panel system is installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.