Weekly Project Update

Horseshoe Bay Fire station No. 2, 07/11/2025

Placeholder

Michael Olmos

Jul 11, 2025

THIS WEEK'S ACCOMPLISHMENT

    Exterior stone veneer at 95% completion
    Finished installation of all door frames
    Continued installation of overhead fire sprinkler system
    Continued installation of overhead HVAC ductwork
    Continued installation of roof insulation
Excavation 1.jpg

Completed stone veneer around plan-West side of building

NEXT WEEK'S ACTIVITIES

    Install metal flashing at top of exterior stone veneer
    Install z-furring channels and exterior rigid insulation
    Start installation of hardi siding
    Make electrical rough in changes according to ASI #1
    Insulate all in-wall plumbing copper lines
Excavation 1.jpg
    Finish installation of roofing insulation

Completed stone veneer around bedroom windows

Excavation 1.jpg

Overhead HVAC duct installation over main corridor

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.