top of page


Weekly Project Update
Horseshoe Bay Fire station No. 2, 07/11/2025

Michael Olmos
Jul 11, 2025
THIS WEEK'S ACCOMPLISHMENT
- Exterior stone veneer at 95% completion
- Finished installation of all door frames
- Continued installation of overhead fire sprinkler system
- Continued installation of overhead HVAC ductwork
- Continued installation of roof insulation
-

Completed stone veneer around plan-West side of building
NEXT WEEK'S ACTIVITIES
- Install metal flashing at top of exterior stone veneer
- Install z-furring channels and exterior rigid insulation
- Start installation of hardi siding
- Make electrical rough in changes according to ASI #1
- Insulate all in-wall plumbing copper lines

- Finish installation of roofing insulation
Completed stone veneer around bedroom windows

Overhead HVAC duct installation over main corridor
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page