Weekly Project Update
Horseshoe Bay Fire Station No. 2, 07/18/2025

Michael Olmos
Jul 18, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed installation of all exterior stone veneer
- Completed installation of all roofing insulation
- Completed installation of fire rated window frames in Apparatus Bay
- Continued installation of overhead MEP rough in
-
-

Continuing installation of overhead HVAC duct over the decon rooms
NEXT WEEK'S ACTIVITIES
- Complete installation of all metal flashing above exterior stone veneer
- Complete installation of all z-furring channels and remaining rigid exterior insulation
- Start installation of exterior hardi siding
- Continue installation of overhead MEP rough in and insulation of copper lines
-

-
All exterior stone veneer around bedroom windows and patio column completed

Exterior stone veneer at front of building completed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.