Weekly Project Update

Horseshoe Bay Fire Station No. 2, 07/18/2025

Placeholder

Michael Olmos

Jul 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed installation of all exterior stone veneer
    Completed installation of all roofing insulation
    Completed installation of fire rated window frames in Apparatus Bay
    Continued installation of overhead MEP rough in
Excavation 1.jpg

Continuing installation of overhead HVAC duct over the decon rooms

NEXT WEEK'S ACTIVITIES

    Complete installation of all metal flashing above exterior stone veneer
    Complete installation of all z-furring channels and remaining rigid exterior insulation
    Start installation of exterior hardi siding
    Continue installation of overhead MEP rough in and insulation of copper lines
Excavation 1.jpg

All exterior stone veneer around bedroom windows and patio column completed

Excavation 1.jpg

Exterior stone veneer at front of building completed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.