top of page


Weekly Project Update
Horseshoe Bay Fire Station No. 2, 08/01/2025

Michael Olmos
Aug 1, 2025
THIS WEEK'S ACCOMPLISHMENT
- Finished in wall rough in changes from ASI 01
- Insulated in wall copper lines
- Installed z-furring channels on exterior
- Installed rigid insulation within exterior z-furring channels
- Continued overhead MEP rough in
-

Relocated alerting system junction boxes to above bedroom doorways
NEXT WEEK'S ACTIVITIES
- Install exterior hardi siding
- Start insulating interior walls
- Start sheetrocking interior walls
- Perform remaining site work for new driveways and parking
- Begin trenching for data lines

-
Exterior z-furring channels and insulation installed

Copper lines insulated within Decon Bathroom chase wall
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page