Weekly Project Update

Horseshoe Bay Fire Station No. 2, 08/01/2025

Placeholder

Michael Olmos

Aug 1, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished in wall rough in changes from ASI 01
    Insulated in wall copper lines
    Installed z-furring channels on exterior
    Installed rigid insulation within exterior z-furring channels
    Continued overhead MEP rough in
Excavation 1.jpg

Relocated alerting system junction boxes to above bedroom doorways

NEXT WEEK'S ACTIVITIES

    Install exterior hardi siding
    Start insulating interior walls
    Start sheetrocking interior walls
    Perform remaining site work for new driveways and parking
    Begin trenching for data lines
Excavation 1.jpg

Exterior z-furring channels and insulation installed

Excavation 1.jpg

Copper lines insulated within Decon Bathroom chase wall

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.