Horseshoe Bay Fire Station No. 2, 08/08/2025

Placeholder

Michael Olmos

Aug 8, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed installation of exterior z-furring channels and rigid insulation
    Completed installation of R-19 exterior wall insulation
    Completed rough in of HVAC overhead ductwork
    Continued installation of electrical overhead rough in
    Started remainder of site work grading
    Started installation of exterior hardi siding
Excavation 1.jpg

Exterior walls in kitchen are insulated

NEXT WEEK'S ACTIVITIES

    Complete remainder of site work grading
    Complete installation of exterior hardi siding
    Start remaining site concrete work
    Finish insulation of interior walls and begin one-siding walls with sheetrock
    Trench lines for data to building and for secondary power to the transformer
Excavation 1.jpg

Z-furring channels and rigid insulation complete

Excavation 1.jpg

Exterior hardi siding at front of building

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.