Weekly Project Update
Horseshoe Bay Fire Station No. 2, 08/08/2025

Michael Olmos
Aug 8, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed installation of exterior z-furring channels and rigid insulation
- Completed installation of R-19 exterior wall insulation
- Completed rough in of HVAC overhead ductwork
- Continued installation of electrical overhead rough in
- Started remainder of site work grading
- Started installation of exterior hardi siding

Exterior walls in kitchen are insulated
NEXT WEEK'S ACTIVITIES
- Complete remainder of site work grading
- Complete installation of exterior hardi siding
- Start remaining site concrete work
- Finish insulation of interior walls and begin one-siding walls with sheetrock
- Trench lines for data to building and for secondary power to the transformer

-
Z-furring channels and rigid insulation complete

Exterior hardi siding at front of building
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.