THIS WEEK'S ACCOMPLISHMENT
- Finished installation of exterior hardi siding
- Finished getting overall site to grade
- Started installing sheetrock throughout building
- Started painting exterior hardi siding
- Started insulating all overhead duct work
- Continued with overhead electric rough in

Sheetrock installed in kitchen
NEXT WEEK'S ACTIVITIES
- Finish painting exterior hardi siding
- Finish all MEP roof penetrations
- Finish installation of roofing
- Start concrete formwork and rebar for sidewalks and driveways
- Start tape / float / paint prep throughout building

- Continue installing sheetrock throughout building