THIS WEEK'S ACCOMPLISHMENT

    Finished installation of exterior hardi siding
    Finished getting overall site to grade
    Started installing sheetrock throughout building
    Started painting exterior hardi siding
    Started insulating all overhead duct work
    Continued with overhead electric rough in
Excavation 1.jpg

Sheetrock installed in kitchen

NEXT WEEK'S ACTIVITIES

    Finish painting exterior hardi siding
    Finish all MEP roof penetrations
    Finish installation of roofing
    Start concrete formwork and rebar for sidewalks and driveways
    Start tape / float / paint prep throughout building
Excavation 1.jpg
    Continue installing sheetrock throughout building

Insulated ductwork over corridor

Excavation 1.jpg

Exterior hardi siding complete

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.