Weekly Project Update

Horseshoe Bay Fire Station No. 2, 08/29/2025

Placeholder

Michael Olmos

Aug 29, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished installation of sheetrock walls
    Finished installation of all roofing
    Finished trenching and installation of data communication lines and secondaries
    Started tape / float / paint prep of all walls
    Stacked fire riser
Excavation 1.jpg

Tape / float / paint prep on hallway walls

NEXT WEEK'S ACTIVITIES

    Finish installation of tape / float / paint prep on all walls
    Start first coat of paint on all walls
    Start formwork and rebar installation for concrete driveways and sidewalks
    Place concrete for all housekeeping pads within building and on mechanical pad
Excavation 1.jpg

Electric homeruns over Apparatus Bay

Excavation 1.jpg

All exterior hardi siding painted

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.