THIS WEEK'S ACCOMPLISHMENT
- Finished installation of sheetrock walls
- Finished installation of all roofing
- Finished trenching and installation of data communication lines and secondaries
- Started tape / float / paint prep of all walls
- Stacked fire riser
-

Tape / float / paint prep on hallway walls
NEXT WEEK'S ACTIVITIES
- Finish installation of tape / float / paint prep on all walls
- Start first coat of paint on all walls
- Start formwork and rebar installation for concrete driveways and sidewalks
- Place concrete for all housekeeping pads within building and on mechanical pad
-

-
Electric homeruns over Apparatus Bay

All exterior hardi siding painted