Weekly Project Update

Horseshoe Bay Fire Station No. 2, 09/05/2025

Placeholder

Michael Olmos

Sep 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished tape / float / and paint prep throughout building
    Finished first coat of paint in areas that receive drop ceilings
    Finished installing formwork and rebar for rear driveway
    Placed concrete for rear driveway and bollards
    Started installation of ceiling grid in bedrooms
Excavation 1.jpg

Ceiling grid installed in bedrooms

NEXT WEEK'S ACTIVITIES

    Install formwork and rebar for front driveway, parking, and housekeeping pads
    Place concrete for front driveway, parking, and housekeeping pads
    Finish installing ceiling grid
    Install fire sprinkler head drops in ceiling grid areas and finish fire sprinkler overhead install
Excavation 1.jpg

All rooms, hallways, and door frames received first coat of paint

Excavation 1.jpg

Placed concrete for rear driveway