THIS WEEK'S ACCOMPLISHMENT
- Finished tape / float / and paint prep throughout building
- Finished first coat of paint in areas that receive drop ceilings
- Finished installing formwork and rebar for rear driveway
- Placed concrete for rear driveway and bollards
- Started installation of ceiling grid in bedrooms
-

Ceiling grid installed in bedrooms
NEXT WEEK'S ACTIVITIES
- Install formwork and rebar for front driveway, parking, and housekeeping pads
- Place concrete for front driveway, parking, and housekeeping pads
- Finish installing ceiling grid
- Install fire sprinkler head drops in ceiling grid areas and finish fire sprinkler overhead install
-

-
All rooms, hallways, and door frames received first coat of paint

Placed concrete for rear driveway