THIS WEEK'S ACCOMPLISHMENT
- Finished formwork, rebar, and concrete placement for front driveway and parking for building
- Finished installing ceiling grid throughout building
- Continued installing overhead for electrical over hard lid ceiling areas
- Continued positioning fire sprinkler head drops over hard lid ceiling areas and within ceiling grid
- Installed exterior louvers for Apparatus Bay, Decon Shop room, and Mechanical room
- Continued installing HVAC supply and return grilles into ceiling grid

Ceiling grid in lobby with HVAC supply and return grilles installed
NEXT WEEK'S ACTIVITIES
- Finish installing fire sprinkler heads into ceiling, hydro test the system
- Install panel cans and run homerun conduit lines through building
- Install sheetrock for hard lid ceiling areas
- Start tape / float / paint prep for hard lid ceiling areas
-

-
Louver for Apparatus Bay installed

Placed concrete for front driveway and parking area
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.