Weekly Project Update

Horseshoe Bay Fire Station No. 2, 09/12/2025

Placeholder

Michael Olmos

Sep 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished formwork, rebar, and concrete placement for front driveway and parking for building
    Finished installing ceiling grid throughout building
    Continued installing overhead for electrical over hard lid ceiling areas
    Continued positioning fire sprinkler head drops over hard lid ceiling areas and within ceiling grid
    Installed exterior louvers for Apparatus Bay, Decon Shop room, and Mechanical room
    Continued installing HVAC supply and return grilles into ceiling grid
Excavation 1.jpg

Ceiling grid in lobby with HVAC supply and return grilles installed

NEXT WEEK'S ACTIVITIES

    Finish installing fire sprinkler heads into ceiling, hydro test the system
    Install panel cans and run homerun conduit lines through building
    Install sheetrock for hard lid ceiling areas
    Start tape / float / paint prep for hard lid ceiling areas
Excavation 1.jpg

Louver for Apparatus Bay installed

Excavation 1.jpg

Placed concrete for front driveway and parking area

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.