THIS WEEK'S ACCOMPLISHMENT
- Installed all floor drains in bathrooms, mechanical room, and bunker room
- Installed HVAC units on mechanical pad and began installing piping to the units
- Installed the panel cans in electrical room
- Installed heater units in Apparatus Bay
- Installed HVAC grilles in ceiling grid and hard lid ceiling areas
-

Installed heater units over Apparatus Bay
NEXT WEEK'S ACTIVITIES
- Install transformer
- Finish fire sprinkler head installation, perform hydro test and inspection
- Install overhead coiling doors
- Start installation of gyp board ceilings
- Continue conduit homeruns for electrical overhead

-
Installed panel cans in electrical room

Installed units on mechanical pad