THIS WEEK'S ACCOMPLISHMENT

    Installed all floor drains in bathrooms, mechanical room, and bunker room
    Installed HVAC units on mechanical pad and began installing piping to the units
    Installed the panel cans in electrical room
    Installed heater units in Apparatus Bay
    Installed HVAC grilles in ceiling grid and hard lid ceiling areas
Excavation 1.jpg

Installed heater units over Apparatus Bay

NEXT WEEK'S ACTIVITIES

    Install transformer
    Finish fire sprinkler head installation, perform hydro test and inspection
    Install overhead coiling doors
    Start installation of gyp board ceilings
    Continue conduit homeruns for electrical overhead
Excavation 1.jpg

Installed panel cans in electrical room

Excavation 1.jpg

Installed units on mechanical pad

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.