THIS WEEK'S ACCOMPLISHMENT

    Finished installation of transformer
    Performed hydro test for sprinkler system, visual inspection scheduled for next week
    Finished installation of framing for ceiling access panels and HVAC grilles
    Installed all hollow metal doors around exterior and within building
    Finished installation of all exterior louvers
Excavation 1.jpg

Hollow metal doors for Mechanical Room installed

NEXT WEEK'S ACTIVITIES

    Start installation of gyp board ceilings
    Start tape / float / paint prep of gyp board ceilings
    Start installation of MDP panel in electrical room
    Install disconnects for overhead coiling doors
Excavation 1.jpg

Final louver installed above Apparatus Bay opening

Excavation 1.jpg

Homeruns installed coming out of panel LR