THIS WEEK'S ACCOMPLISHMENT
- Finished installation of transformer
- Performed hydro test for sprinkler system, visual inspection scheduled for next week
- Finished installation of framing for ceiling access panels and HVAC grilles
- Installed all hollow metal doors around exterior and within building
- Finished installation of all exterior louvers
-

Hollow metal doors for Mechanical Room installed
NEXT WEEK'S ACTIVITIES
- Start installation of gyp board ceilings
- Start tape / float / paint prep of gyp board ceilings
- Start installation of MDP panel in electrical room
- Install disconnects for overhead coiling doors
-

-
Final louver installed above Apparatus Bay opening

Homeruns installed coming out of panel LR