THIS WEEK'S ACCOMPLISHMENT

    Finished installing all sheetrock ceilings
    Tape / float / and paint prepped hard lid ceilings in bathrooms, kitchen, decon rooms, electrical room and utility room
    Installed FCU units in Mechanical Room
    Started prepping restrooms for ceramic tile installation
    Grinder pump is installed
    Installed lighting whips for living quarters
Excavation 1.jpg

FCUs installed in Mechanical Room

NEXT WEEK'S ACTIVITIES

    Finish tape / float / and paint prep for sheetrock ceilings
    Perform sealed concrete work for Apparatus Bay, Decon rooms, passage ways, and electrical and mechanical rooms
    Install overhead coiling doors in Apparatus Bay
    Begin building MDP panel for power
    Continue installation of ceramic tile in restrooms
Excavation 1.jpg

Shower pan in restroom floated

Excavation 1.jpg

Sheetrock installed for Apparatus Bay ceiling

LOOK AHEAD SCHEDULE