Weekly Project Update
Horseshoe Bay Fire Station No. 2, 10/17/2025

Michael Olmos
Oct 17, 2025
THIS WEEK'S ACCOMPLISHMENT
- Installed blockfiller on CMU walls in Decon rooms, first coated CMU walls
- Started ceramic tile installation on restroom floors
- Sealed concrete floor in Apparatus Bay
- Continued building MDP in electrical room
- Continued installing conduit runs for lighting and fans for kitchen and day room
- Finished installing refrigerant lines and condensate lines for FCUs in mechanical room

CMU walls in Decon rooms first coated
NEXT WEEK'S ACTIVITIES
- Install canopies
- Finish installing ceramic tile in restrooms
- Seal concrete floors in Decon rooms, Mechanical Room and Electrical Room
- Finish building MDP, build meter service
- Install overhead coiling doors in Apparatus Bay

- Tape / float / prime and first coat ceiling in Apparatus Bay
Refrigerant and condensate lines installed for FCUs

Flooring tile installed in restrooms
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.