Weekly Project Update

Horseshoe Bay Fire Station No. 2, 10/17/2025

Placeholder

Michael Olmos

Oct 17, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed blockfiller on CMU walls in Decon rooms, first coated CMU walls
    Started ceramic tile installation on restroom floors
    Sealed concrete floor in Apparatus Bay
    Continued building MDP in electrical room
    Continued installing conduit runs for lighting and fans for kitchen and day room
    Finished installing refrigerant lines and condensate lines for FCUs in mechanical room
Excavation 1.jpg

CMU walls in Decon rooms first coated

NEXT WEEK'S ACTIVITIES

    Install canopies
    Finish installing ceramic tile in restrooms
    Seal concrete floors in Decon rooms, Mechanical Room and Electrical Room
    Finish building MDP, build meter service
    Install overhead coiling doors in Apparatus Bay
Excavation 1.jpg
    Tape / float / prime and first coat ceiling in Apparatus Bay

Refrigerant and condensate lines installed for FCUs

Excavation 1.jpg

Flooring tile installed in restrooms

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.