THIS WEEK'S ACCOMPLISHMENT

    Installed blockfiller on CMU walls in Apparatus Bay
    Primed sheetrock ceiling in Apparatus Bay
    Continued ceramic tile installation in restrooms
    Installed fire alarm control panel
    Installed overhead coiling doors
Excavation 1.jpg

Installed fire alarm control panel

NEXT WEEK'S ACTIVITIES

    Finish ceramic tile installation
    Install ATS and Docking Station
    Start and complete secondary service connection
    Receive exterior service inspection
Excavation 1.jpg

Walls and ceiling in Apparatus Bay first coat of paint

Excavation 1.jpg

Installed overhead coiling doors for Apparatus Bay