THIS WEEK'S ACCOMPLISHMENT

    Set ATS on Mechanical Pad
    Mounted building meter and service disconnect on building next to ATS
    Finished installing ceramic tile in restrooms
    Finished installing HVAC grilles in sheetrock ceilings
    Started installing exterior canopies
    Started pulling wire from transformer to meter on building
Excavation 1.jpg

Exterior 5' x 5' canopies installed

NEXT WEEK'S ACTIVITIES

    Install plumbing fixtures in restrooms
    Finish pulling wire to building meter and energize building
    Begin HVAC startup
    Finish installing exterior canopies
    Begin final site backfill to finished grade
Excavation 1.jpg

Ceramic tile in restrooms installed

Excavation 1.jpg

ATS, Meter, and Service Disconnect installed on exterior of building