Weekly Project Update
Horseshoe Bay Fire Station No. 2, 10/31/2025

Michael Olmos
Oct 31, 2025
THIS WEEK'S ACCOMPLISHMENT
- Set ATS on Mechanical Pad
- Mounted building meter and service disconnect on building next to ATS
- Finished installing ceramic tile in restrooms
- Finished installing HVAC grilles in sheetrock ceilings
- Started installing exterior canopies
- Started pulling wire from transformer to meter on building

Exterior 5' x 5' canopies installed
NEXT WEEK'S ACTIVITIES
- Install plumbing fixtures in restrooms
- Finish pulling wire to building meter and energize building
- Begin HVAC startup
- Finish installing exterior canopies
- Begin final site backfill to finished grade

-
Ceramic tile in restrooms installed

ATS, Meter, and Service Disconnect installed on exterior of building
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.