THIS WEEK'S ACCOMPLISHMENT
- Finished overhead electrical conduit runs
- Finished building exterior service connection, received green tag from ATS Inspector
- Installed fire rated glass for Apparatus Bay windows
- Started installing plumbing fixtures
- Started final site backfill and spoils haul off
-

Installed FCU disconnects in mechanical room
NEXT WEEK'S ACTIVITIES
- Begin HVAC start-up
- Continue running wire throughout building
- Prep site for landscaping and hydroseeding
- Install temporary irrigation
- Start prep work for LVT flooring

-
Wire run through conduit lines to junction boxes and homeruns

Building meter inspected and green tagged by city