THIS WEEK'S ACCOMPLISHMENT

    Finished overhead electrical conduit runs
    Finished building exterior service connection, received green tag from ATS Inspector
    Installed fire rated glass for Apparatus Bay windows
    Started installing plumbing fixtures
    Started final site backfill and spoils haul off
Excavation 1.jpg

Installed FCU disconnects in mechanical room

NEXT WEEK'S ACTIVITIES

    Begin HVAC start-up
    Continue running wire throughout building
    Prep site for landscaping and hydroseeding
    Install temporary irrigation
    Start prep work for LVT flooring
Excavation 1.jpg

Wire run through conduit lines to junction boxes and homeruns

Excavation 1.jpg

Building meter inspected and green tagged by city