THIS WEEK'S ACCOMPLISHMENT

    Started installation of millwork in kitchen, bedrooms, bathrooms, and utility room
    Started installation of 2x2 light fixtures in corridors
    Started installation of light fixtures in Apparatus Bay
    Installed emergency lights throughout building
    Ran wire for all lighting homeruns
Excavation 1.jpg

Millwork in bedroom

NEXT WEEK'S ACTIVITIES

    Perform HVAC startup and create a conditioned space
    Finish installing light fixtures and have them operational
    Finish installing countertops
    Start installation of ceramic tile in kitchen
    Start installation of accessories throughout building and restrooms
Excavation 1.jpg
    Set plumbing fixtures and kitchen equipment

2x2 light fixtures installed in corridor

Excavation 1.jpg

Kitchen millwork for fridge area

LOOK AHEAD SCHEDULE