Weekly Project Update
Horseshoe Bay Fire Station No. 2, 11/21/2025

Michael Olmos
Nov 21, 2025
THIS WEEK'S ACCOMPLISHMENT
- Started installation of millwork in kitchen, bedrooms, bathrooms, and utility room
- Started installation of 2x2 light fixtures in corridors
- Started installation of light fixtures in Apparatus Bay
- Installed emergency lights throughout building
- Ran wire for all lighting homeruns
-

Millwork in bedroom
NEXT WEEK'S ACTIVITIES
- Perform HVAC startup and create a conditioned space
- Finish installing light fixtures and have them operational
- Finish installing countertops
- Start installation of ceramic tile in kitchen
- Start installation of accessories throughout building and restrooms

- Set plumbing fixtures and kitchen equipment
2x2 light fixtures installed in corridor

Kitchen millwork for fridge area
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.