Weekly Project Update

Horseshoe Bay Fire Station No. 2, 12/05/2025

Placeholder

Michael Olmos

Dec 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Energized all lights in building
    Installed all LVT flooring
    Installed bunker gear lockers
    Finished building rack in IDF room
    Started final coat of paint through whole building
    Connected wiring from ATS to MTS to Generator unit
Excavation 1.jpg

Light fixtures and ceiling fans in Day Room

NEXT WEEK'S ACTIVITIES

    Finish final coat of paint
    Install window shades
    Finish all lighting controls and power receptacles
    Finish dropping all ceiling tile
    Install all remaining doors and hardware
Excavation 1.jpg

Gear lockers installed in Bunker Room

Excavation 1.jpg

Light fixtures and flooring installed in kitchen

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.