top of page


Weekly Project Update
Horseshoe Bay Fire Station No. 2, 12/05/2025

Michael Olmos
Dec 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- Energized all lights in building
- Installed all LVT flooring
- Installed bunker gear lockers
- Finished building rack in IDF room
- Started final coat of paint through whole building
- Connected wiring from ATS to MTS to Generator unit

Light fixtures and ceiling fans in Day Room
NEXT WEEK'S ACTIVITIES
- Finish final coat of paint
- Install window shades
- Finish all lighting controls and power receptacles
- Finish dropping all ceiling tile
- Install all remaining doors and hardware

-
Gear lockers installed in Bunker Room

Light fixtures and flooring installed in kitchen
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page