Weekly Project Update

Horseshoe Bay Fire Station No. 2, 12/12/2025

Placeholder

Michael Olmos

Dec 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Finished final paint
    Finished all exterior lighting
    Finished flooring and cove base
    Finished door hardware
    Performed final clean of building
Excavation 1.jpg

Window blinds installed in lobby

NEXT WEEK'S ACTIVITIES

    Receive final fire alarm inspection
    Receive final MEP inspections
    Receive final building inspection
    Receive final fire inspection
Excavation 1.jpg

Door hardware installed on Bunker Room door

Excavation 1.jpg

Can lights and ceiling fan installed at patio

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.