THIS WEEK'S ACCOMPLISHMENT
- Finished final paint
- Finished all exterior lighting
- Finished flooring and cove base
- Finished door hardware
- Performed final clean of building
-

Window blinds installed in lobby
NEXT WEEK'S ACTIVITIES
- Receive final fire alarm inspection
- Receive final MEP inspections
- Receive final building inspection
- Receive final fire inspection
-

-
Door hardware installed on Bunker Room door

Can lights and ceiling fan installed at patio