Weekly Project Update
HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- Received Electric Panel HEN and Gear for HWC Panel
- Connected Power to AHU #9 and Associated Condensers
- Completed AHU #9 Coil Installation, Refrigerant Line Pressure Testing & Insulation
- Completed Sprinkler Head Relocation in Gathering Room
- Continue Ceramic Wall & Floor Tile Installation
- Start School Administration Area Flooring Renovation

HWC Panel Installation
NEXT WEEK'S ACTIVITIES
- Start-up of AHU #9
- Complete Flooring Renovation @ School Administration Area
- Continue Ceramic Floor and Wall Tile Installation
- Complete Fire Sprinkler Head Relocation
- Complete Painting @ School Administration Area

- Continue AHU New Coil Installation
Prime and 1st Finish Coat on New Chair-rail

Ceramic Floor & Wall Tile @ Staff Restroom and Locker Area
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.