Weekly Project Update

HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Complete Setting Condensers for AHU #9 & AHU #10 on Roof
    Complete Wood Fence Enclosures @ New Mechanical Yards
    Complete Texturing Walls
    Start Prime & 1st Finish Paint @ All Walls
    Continue Pulling Wire in Conduit
    Finalize Color Selections for Ceramic Tile, Wall Paint, Solid Surface Tops & Laminate @ Millwork
Excavation 1.jpg

New Condensers for AHU #9 & #10, Refrigerant Piping, Existing Kitchen Hood Exhaust Fan

NEXT WEEK'S ACTIVITIES

    Continue Painting @ All Walls
    Continue Ceiling Grid
    Start Plaster Repair
    Start Ceramic Tile Installation
    Continue Electric Wire Installation
Excavation 1.jpg
    Connect Duct & Refrigerant Lines to AHU 7.1 & AHU 7.2

Painting 1st Finish Coat @ Gathering Room Fur-Downs

Excavation 1.jpg

New Wood Fencing @ NE Mechanical Yard

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.