Weekly Project Update

HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    New Building Switchgear in Place
    Start Installation of Breakers in Selected Electric Panels
    Install Fire Alarm Device(s) in Ceilings & Walls
    Start Relocating Fire Sprinkler Heads in New Ceiling Grid
    Continue Refrigerant Piping Installation to new Condensers
    Start Ceramic Rile Installation @ Prep Room & Caterer Kitchen
Excavation 1.jpg

New Building Switchgear

NEXT WEEK'S ACTIVITIES

    Continue to Extend Electric Service to AHU #9 & #10
    Secure Electric O/H Cover-up Inspection from COA
    Continue Relocating Fire Sprinkler Heads in Ceiling Grid
    Complete Duct Installation
    Start Plaster Wall Repair
Excavation 1.jpg
    Continue Ceramic Tile @ Caterer Kitchen

Caterer Kitchen Ceramic Tile - Typical

Excavation 1.jpg

Ceramic Tile @ New PREP Room

LOOK AHEAD SCHEDULE