Weekly Project Update
HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATION
Nathan Barry
THIS WEEK'S ACCOMPLISHMENT
- New Building Switchgear in Place
- Start Installation of Breakers in Selected Electric Panels
- Install Fire Alarm Device(s) in Ceilings & Walls
- Start Relocating Fire Sprinkler Heads in New Ceiling Grid
- Continue Refrigerant Piping Installation to new Condensers
- Start Ceramic Rile Installation @ Prep Room & Caterer Kitchen
New Building Switchgear
NEXT WEEK'S ACTIVITIES
- Continue to Extend Electric Service to AHU #9 & #10
- Secure Electric O/H Cover-up Inspection from COA
- Continue Relocating Fire Sprinkler Heads in Ceiling Grid
- Complete Duct Installation
- Start Plaster Wall Repair
- Continue Ceramic Tile @ Caterer Kitchen
Caterer Kitchen Ceramic Tile - Typical
Ceramic Tile @ New PREP Room
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.