Weekly Project Update

HYDE PARK BAPTIST CHURCH - BASEMENT RENOVATIONS

Placeholder

Nathan Barry

THIS WEEK'S ACCOMPLISHMENT

    Start Slab Demo to uncovering UG Plumbing Piping for new Restrooms
    Continue O/H Electric Conduit Rough
    Start Wall Demo
    Continue Supply Duct Sealing and Insulation Wrap
    Start New Wall Framing
    Continue Ceiling Fur-Downs in Gathering Room
Excavation 1.jpg

Slab Demo for Plumbing @ New Restrooms

NEXT WEEK'S ACTIVITIES

    Complete Ceiling Fur-Down Framing
    Continue New Wall Framing
    Start U/G Plumbing Rough @ New Restrooms
    Complete All Wall Demo
    Continue Electric Conduit Rough
Excavation 1.jpg
    Continue Re-installing Hollow Metal Frames

Basement Renovation Floor Plan

Excavation 1.jpg

GATHERING ROOM Ceiling Fur-down Framing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.