THIS WEEK'S ACCOMPLISHMENT

    Bathroom toilet and urinals installed in both women's and men's bathroom
    Bathroom tile work for both men's and women's bathroom complete.
    Tile for baseboard around new construction and hallway complete
    Working on ceiling tile borders
    added 4 sprinkler heads. complete the lowering and centering of sprinkler heads
Excavation 1.jpg

Toilets for bathrooms installed

NEXT WEEK'S ACTIVITIES

    Complete ceiling borders
    Install partitions for bathrooms
    Install and turn lights on
    install millwork for bathrooms
    Complete remaining plumbing IE: sinks
Excavation 1.jpg
    Install ceiling tile

Ceiling tile borders in progress

Excavation 1.jpg

Tile baseboard installed and completed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.