top of page


Weekly Project Update
Hyde Park Baptist Church

Martin Diaz
Nov 21, 2025
THIS WEEK'S ACCOMPLISHMENT
- Worked and completed bathroom rough inn, for both the men and women's bathroom
- Started framing ceilings, after meeting with the architect to discuss layout of lights and A/C vent grills.
- Install electrical floor box
-
-
-

Painter contractor is 100% complete with first coat of paint
NEXT WEEK'S ACTIVITIES
- The flooring company will work to level the floors to get ready to install LVT flooring
- Bathrooms wall tile will start for both bathrooms.
-
-
-

-
Plumbing rough in is complete

Ceiling has started and is ongoing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page