Weekly Project Update

Hyde Park Baptist Church

Placeholder

Martin Diaz

Nov 21, 2025

THIS WEEK'S ACCOMPLISHMENT

    Worked and completed bathroom rough inn, for both the men and women's bathroom
    Started framing ceilings, after meeting with the architect to discuss layout of lights and A/C vent grills.
    Install electrical floor box
Excavation 1.jpg

Painter contractor is 100% complete with first coat of paint

NEXT WEEK'S ACTIVITIES

    The flooring company will work to level the floors to get ready to install LVT flooring
    Bathrooms wall tile will start for both bathrooms.
Excavation 1.jpg

Plumbing rough in is complete

Excavation 1.jpg

Ceiling has started and is ongoing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.