Weekly Project Update
Hyde Park Baptist Church

Martin Diaz
Nov 14, 2025
THIS WEEK'S ACCOMPLISHMENT
- Complete install of all Blocking for Partitions, Mirrors and Baby changer. And verified that it will work according to the measurements given by subs
- Installed and completed all gyp board for the ceilings and walls.
- Complete the tape and float of walls. Sand and prime walls in the main lobby area.
- Install first coat of paint in main lobby area.
- Bathrooms tape and float in the bathroom ceilings.
-

All blocking in bathrooms complete
NEXT WEEK'S ACTIVITIES
- Electrician will start and complete rough inn for lights.
- Install ceiling grid in main lobby area.
- Wall Tile in bathrooms get started
- Complete first coat of paint in bathrooms
-

-
All gyp board in bathrooms completed

Primer and 1st coat of Paint installed in main lobby area
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.