Weekly Project Update

Hyde Park Baptist Church

Placeholder

Martin Diaz

Nov 14, 2025

THIS WEEK'S ACCOMPLISHMENT

    Complete install of all Blocking for Partitions, Mirrors and Baby changer. And verified that it will work according to the measurements given by subs
    Installed and completed all gyp board for the ceilings and walls.
    Complete the tape and float of walls. Sand and prime walls in the main lobby area.
    Install first coat of paint in main lobby area.
    Bathrooms tape and float in the bathroom ceilings.
Excavation 1.jpg

All blocking in bathrooms complete

NEXT WEEK'S ACTIVITIES

    Electrician will start and complete rough inn for lights.
    Install ceiling grid in main lobby area.
    Wall Tile in bathrooms get started
    Complete first coat of paint in bathrooms
Excavation 1.jpg

All gyp board in bathrooms completed

Excavation 1.jpg

Primer and 1st coat of Paint installed in main lobby area

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.