Weekly Project Update
Hyde Park Baptist Church

Martin Diaz
Nov 10, 2025
THIS WEEK'S ACCOMPLISHMENT
- Main Lobby fur down framed
- Main lobby Gyp board is installed
- Corners for the entire lobby area complete
-
-
-

Start to cover framing with gyp board
NEXT WEEK'S ACTIVITIES
- Install blocking in bathrooms for the new partitions, mirror and casework
- Install gyp in bathrooms on ceiling
- install gup board for Tile work in both bathrooms
- Start tape and float in main lobby area.
-

-
Covered all framing with gyp board

Install trim work on gyp board. getting ready for tape and float
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.