Weekly Project Update

Hyde Park Baptist Church

Placeholder

Martin Diaz

Dec 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Flooring prep work completed and started to flooring work
    The Floor for the entire area is complete
    Wall tile was delivered
    The wall tile for the bathrooms has started on women's bathroom
    16 ft. light strips started to be framed. only three lights of nine have been completed.
Excavation 1.jpg

Ceiling grid complete. light strips being framed.

NEXT WEEK'S ACTIVITIES

    Wall tile will be completed for both restrooms
    Plumbing contractor will start install of plumbing fixtures
    The remaining lights strips will be completed.
    Electrician will start installing light fixtures
    Sprinkler contractor start install of 4 new sprinkler heads, and adjust existing sprinkler heads
Excavation 1.jpg
    Ceiling borders will be in progess.

new flooring installed completed

Excavation 1.jpg

Wall tile started in bathrooms

LOOK AHEAD SCHEDULE