Weekly Project Update
Hyde Park Baptist Church

Martin Diaz
Dec 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- Flooring prep work completed and started to flooring work
- The Floor for the entire area is complete
- Wall tile was delivered
- The wall tile for the bathrooms has started on women's bathroom
- 16 ft. light strips started to be framed. only three lights of nine have been completed.
-

Ceiling grid complete. light strips being framed.
NEXT WEEK'S ACTIVITIES
- Wall tile will be completed for both restrooms
- Plumbing contractor will start install of plumbing fixtures
- The remaining lights strips will be completed.
- Electrician will start installing light fixtures
- Sprinkler contractor start install of 4 new sprinkler heads, and adjust existing sprinkler heads

- Ceiling borders will be in progess.
new flooring installed completed

Wall tile started in bathrooms
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.