THIS WEEK'S ACCOMPLISHMENT
- Held Pre-con with LCRA, Owners, and Travis County
- CE excavating in STA: 10+66 area and took out storm drain
- Acquired infrastructure permit from WD #17
- Held Pre-con meeting with Kinney's Plumbing and Texas Roofing
- JR Schneider started excavation in detention pond, WQ #2, & Spillman Loop
- A lot of RCP, pipe casings, gravel, and excavation equipment were delivered this week

One of the multiple stacks of RCP
NEXT WEEK'S ACTIVITIES
- Continue excavation on detention pond
- Removal of concrete curbs and dirt work on bus loop
- Continue installing storm drain line SS-A
- Complete wire pull in existing school
- Start roof and wall penetrations for plumbing in existing school

-