Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Feb 6, 2026

THIS WEEK'S ACCOMPLISHMENT

    Officially started all high roof work.
    Continued all MEP rough-in on L-1.
    Began exterior soffit framing in both areas.
    Began laying out L-2 walls.
    Conducted a Low Voltage/IT coordination meeting with LTISD representatives present.
    Continued L-1 wall framing.
Excavation 1.jpg

L-1 MEP rough-in progress.

NEXT WEEK'S ACTIVITIES

    Continue all MEP rough-in on L-1.
    Continue site civil concrete work.
    Continue high roof work.
    Begin L-2 interior wall framing.
    Begin L-2 CMU wall for elevator shaft.
Excavation 1.jpg
    Install scaffolding system for L-2 South wall work.

L-1 exterior wall framing progress.

Excavation 1.jpg

High roof work started.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.