THIS WEEK'S ACCOMPLISHMENT
- Officially started all high roof work.
- Continued all MEP rough-in on L-1.
- Began exterior soffit framing in both areas.
- Began laying out L-2 walls.
- Conducted a Low Voltage/IT coordination meeting with LTISD representatives present.
- Continued L-1 wall framing.

L-1 MEP rough-in progress.
NEXT WEEK'S ACTIVITIES
- Continue all MEP rough-in on L-1.
- Continue site civil concrete work.
- Continue high roof work.
- Begin L-2 interior wall framing.
- Begin L-2 CMU wall for elevator shaft.

- Install scaffolding system for L-2 South wall work.
L-1 exterior wall framing progress.

High roof work started.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.