Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Dec 12, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continued MEP Overhead rough-in and layout.
    Began laying out L-1 interior walls.
    Placed L-2 slab on metal deck.
    Began constructing the CMU wall for the elevator.
Excavation 1.jpg

CMU wall for the elevator.

NEXT WEEK'S ACTIVITIES

    Continue interior wall layout on L-1.
    Continue building CMU wall for the elevator.
    Begin all MEP overhead rough-in for L-1.
    Start FRP for Board Form Finish concrete walls and columns for L-2.
    Continue installing French Drain system and roof drain tie-in.
Excavation 1.jpg

L-2 slab on metal deck placement.

Excavation 1.jpg

L-2 slab on metal deck.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.