top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Dec 12, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continued MEP Overhead rough-in and layout.
- Began laying out L-1 interior walls.
- Placed L-2 slab on metal deck.
- Began constructing the CMU wall for the elevator.
-
-

CMU wall for the elevator.
NEXT WEEK'S ACTIVITIES
- Continue interior wall layout on L-1.
- Continue building CMU wall for the elevator.
- Begin all MEP overhead rough-in for L-1.
- Start FRP for Board Form Finish concrete walls and columns for L-2.
- Continue installing French Drain system and roof drain tie-in.

-
L-2 slab on metal deck placement.

L-2 slab on metal deck.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page