top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jan 16, 2026
THIS WEEK'S ACCOMPLISHMENT
- Placed the remaining 3 Board Form Finish Columns on L-2.
- Began setting joists on L-2.
- Continued L-2 structural steel erection.
- Continued L-1 MEP overhead rough-in.
- Continued interior and exterior wall framing on L-1.
-

MEP rough-in continuing on L-1
NEXT WEEK'S ACTIVITIES
- Continue all L-2 structural steel.
- Continue MEP rough-in on L-1.
- Continue L-1 interior and exterior wall framing.
- Ductwork to be delivered onsite and start hanging overhead duct and mechanical units.
- Begin fence installation around WQ Pond.

-
Structural steel progress L-2.

Joists on L-2.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page