Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Jan 16, 2026

THIS WEEK'S ACCOMPLISHMENT

    Placed the remaining 3 Board Form Finish Columns on L-2.
    Began setting joists on L-2.
    Continued L-2 structural steel erection.
    Continued L-1 MEP overhead rough-in.
    Continued interior and exterior wall framing on L-1.
Excavation 1.jpg

MEP rough-in continuing on L-1

NEXT WEEK'S ACTIVITIES

    Continue all L-2 structural steel.
    Continue MEP rough-in on L-1.
    Continue L-1 interior and exterior wall framing.
    Ductwork to be delivered onsite and start hanging overhead duct and mechanical units.
    Begin fence installation around WQ Pond.
Excavation 1.jpg

Structural steel progress L-2.

Excavation 1.jpg

Joists on L-2.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.