THIS WEEK'S ACCOMPLISHMENT

    Made good progress on all MEP L-1 rough-in.
    Completed CMU wall for the elevator shaft.
    New fence panels on the added sidewalk along Spillman were installed.
    Exterior wall framing along with soffit framing on L-1 made good progress.
    Conducted another Low Voltage/IT coordination meeting with LTISD representatives in attendance.
    L-2 plumbing rough-in has begun.
Excavation 1.jpg

L-2 CMU for elevator shaft.

NEXT WEEK'S ACTIVITIES

    L-2 exterior and interior wall framing material to be onsite.
    Continue all MEP L-1 OH and wall rough-in.
    High roof and low roof work to continue.
    New fencing panels around Water Quality Pond to be installed.
    L-1 exterior wall waterproofing to start.
Excavation 1.jpg
    OAC meeting on Thursday, 02/19/2026.

Soffit framing progress on L-1.

Excavation 1.jpg

New fencing panels for added sidewalk along Spillman installed.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.