top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Feb 13, 2026
THIS WEEK'S ACCOMPLISHMENT
- Made good progress on all MEP L-1 rough-in.
- Completed CMU wall for the elevator shaft.
- New fence panels on the added sidewalk along Spillman were installed.
- Exterior wall framing along with soffit framing on L-1 made good progress.
- Conducted another Low Voltage/IT coordination meeting with LTISD representatives in attendance.
- L-2 plumbing rough-in has begun.

L-2 CMU for elevator shaft.
NEXT WEEK'S ACTIVITIES
- L-2 exterior and interior wall framing material to be onsite.
- Continue all MEP L-1 OH and wall rough-in.
- High roof and low roof work to continue.
- New fencing panels around Water Quality Pond to be installed.
- L-1 exterior wall waterproofing to start.

- OAC meeting on Thursday, 02/19/2026.
Soffit framing progress on L-1.

New fencing panels for added sidewalk along Spillman installed.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page