Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Oct 10, 2025

THIS WEEK'S ACCOMPLISHMENT

    Placed concrete walls in Area A.
    Placed the remaining Grade Beams in Area A.
    Plumbing rough-in passed inspection.
    Grading in Detention Pond #1 progressed.
    Biofiltration material installed at WQ#2.
Excavation 1.jpg

Placement of walls and remaining grad beams in Area A.

NEXT WEEK'S ACTIVITIES

    Place SOG for Area A.
    Continue FRP for walls/columns.
    Continue MEP rough-in in Area B.
    Continue work at Detention Pond #1.
    Weekly Project Update Meeting Thursday, 10/16/2025.
Excavation 1.jpg

Biofiltration installation progress.

Excavation 1.jpg

Progress on Detention Pond #1.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.