Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Oct 10, 2025
THIS WEEK'S ACCOMPLISHMENT
- Placed concrete walls in Area A.
- Placed the remaining Grade Beams in Area A.
- Plumbing rough-in passed inspection.
- Grading in Detention Pond #1 progressed.
- Biofiltration material installed at WQ#2.
-

Placement of walls and remaining grad beams in Area A.
NEXT WEEK'S ACTIVITIES
- Place SOG for Area A.
- Continue FRP for walls/columns.
- Continue MEP rough-in in Area B.
- Continue work at Detention Pond #1.
- Weekly Project Update Meeting Thursday, 10/16/2025.

-
Biofiltration installation progress.

Progress on Detention Pond #1.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.