Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Oct 31, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continued slab reinforcement in Area B.
    Continued FRP on walls for level 1.
    Placed 160yds of Slab On Grade in Area B.
    Placed the first Board From Finish wall for level 1.
Excavation 1.jpg

Placement of SOG B

NEXT WEEK'S ACTIVITIES

    Continue FRP for footings, walls, and columns.
    Start waterproofing on exterior walls.
    Place Board Form Finish columns and walls for level 1.
    Set oil separator tank.
Excavation 1.jpg

Placement of SOG B

Excavation 1.jpg

SOG B

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.