Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Oct 31, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continued slab reinforcement in Area B.
- Continued FRP on walls for level 1.
- Placed 160yds of Slab On Grade in Area B.
- Placed the first Board From Finish wall for level 1.
-
-

Placement of SOG B
NEXT WEEK'S ACTIVITIES
- Continue FRP for footings, walls, and columns.
- Start waterproofing on exterior walls.
- Place Board Form Finish columns and walls for level 1.
- Set oil separator tank.
-

-
Placement of SOG B

SOG B
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.