Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Oct 24, 2025

THIS WEEK'S ACCOMPLISHMENT

    Began forming Board Form Finish walls in Area A.
    Continued FRP on grade beams, walls and columns in Area B.
    Placed exterior walls in Area B.
    Placed remaining grade beams in Area B.
    Continued Slab on Grade reinforcement in Area B.
Excavation 1.jpg

Placing walls in Area B.

NEXT WEEK'S ACTIVITIES

    Continue Slab on Grade reinforcement in Area B.
    Start waterproofing on exterior walls.
    Continue FRP for walls and columns.
    Place Slab on Grade in Area B.
Excavation 1.jpg

Began forming of Board Form Finish walls in Area A.

Excavation 1.jpg

Placed remaining grade beams in Area B.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.