top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Oct 24, 2025
THIS WEEK'S ACCOMPLISHMENT
- Began forming Board Form Finish walls in Area A.
- Continued FRP on grade beams, walls and columns in Area B.
- Placed exterior walls in Area B.
- Placed remaining grade beams in Area B.
- Continued Slab on Grade reinforcement in Area B.
-

Placing walls in Area B.
NEXT WEEK'S ACTIVITIES
- Continue Slab on Grade reinforcement in Area B.
- Start waterproofing on exterior walls.
- Continue FRP for walls and columns.
- Place Slab on Grade in Area B.
-

-
Began forming of Board Form Finish walls in Area A.

Placed remaining grade beams in Area B.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page